MANAGER’S
REPORT
City Council Meeting
Tuesday, July 17, 2007
TO: Mayor and Honorable City Councilors
FROM: Joe Slocum, City Manager
DATE: Friday, July 13, 2007
11.B Discussion and Action on bid opening WWTF.
The Pollution Control Facility has a 40-year-old influent motor control
system (3 liquid rheostats) that has been rebuilt twice and needed
additional modifications this summer. Typical of these older systems-parts are
no longer available and must be custom (think expensive) made. We will need to
upgrade our pumps in a year or so and realized that our controls system would
not last until then without modification. With our engineers guidance we created
specifications and put the three VFD control systems out to bid. We have 2 bids
and I recommend the lower bid be awarded to Stultz Electric for $12,007. (Gold)
This exercise highlights the importance to ratepayers and taxpayers of public
bidding. The lower bid is about half of the next higher bid. Good for us!
11.C Acceptance of Project Canopy Grant.
We need to accept a State Grant in the amount of $3,000. We will provide match
partially with cash and partially with in-kind services (labor, back hoe etc.)
The money will come from the Tree Planting line found in the Budget at 460 678.
I want to thank those associated with Green Streets for putting together such a
professional application. The quality of the application makes it easier for the
State to say yes and to look more favorably upon future applications. (Orchid)
11.D Electrical Quotes for expanded electric
service at Steamboat Landing. With the Masker’s request to use Steam
Boat Landing for summer performances we became aware of electrical deficiencies
associated with this type of use. We have secured quotes from Ron’s Electric. (Green)
There are 2 prices. The first is for $2,200, which will put power along the tree
line and tie directly into the Boat House. He has another quote for putting in a
separate meter for this service for $1,700. This is quite a bit of extra money
for an uncertain number of events per year. Since we presently do not have any
money budgeted for this the funds would have to come from surplus.
If the Council desires to meet these electrical needs then,
I recommend that users not only pay the cost of electricity but also pay an
amount toward repayment to the City for the original installation of this
infrastructure. I recommend a fee of $250 plus the cost of a good faith estimate
of electrical use per event. This summer’s maskers’ event would constitute a
single event. If we spend $2,200 now it will take 8.8 events to pay us back. If
we spend the entire $3,900 it would take 15.6 events to pay us back. The Maskers
event would be treated as a single event.
Since we have not developed a long term plan for outdoor
event use at Steamboat Landing and because I see no great value in paying the
power company for an extra meter every month -I recommend we do not set up a
separate meter at this time. We can do a good faith estimate of electrical use
by comparing past year monthly usage. This is not exact, but it could work
practically.
11.E Consideration of Moving $2,200 from
surplus account to repair oil pan for parks and recreation bus.
We have a bus account line where income is deposited and from where expenses are
withdrawn. It presently carries a negative balance of about $500. We have no
other account to fund repairs to this bus.
This is a 1998 diesel bus with about 90,000 miles on it. In
speaking with Jim Bell, I learned that historically the Council insisted this
bus essentially pay for itself. Jim has done a lot with this bus and I have run
into people who have indicated that they appreciated this activity very much.
I have several concerns:
- This is a single person department – when it started
there was no responsibility for busses, range ways or ball fields gifted from
Bank of America;
- This bus is servicing a need that has nothing to do with
the City of Belfast;
- Jim has tried to incorporate the bus into specific parks
programs (trips- sports opportunities) and the citizens of Belfast have not
responded;
- the bus is rented out at less than half the price of
commercial charter transportation;
- we are losing money and many local groups are
essentially getting the bus itself for free;
- the MSAD #34 Bus Garage also charters busses and has
their own full time staff and mechanics.
I attached Jim Bell’s memo to me dated July 11, 2007. He
charges about $13.00/ hr for the driver, plus $20/hour for the bus. Note our
past renters:
Certain local groups/ events have been getting a price
break:
- Downtown Business Group (Cruise Ships) pays driver and ½
price bus ($10 per hr.)
- Celtic Festival - pays driver only- nothing for bus
- Belfast Maskers “ “
- Boat Building “
“
- Arts in the Park “
“
All of the bookings in Jim’s memo of July 11th
are not likely to cover the cost of replacing the damaged oil pan. I think this
repair must be made to reduce the risk of a far greater mechanical breakdown. I
ask Council to transfer the sum of $2,200 from surplus to prevent further
serious damage.
It is really unrealistic to expect this bus to pay for
itself. Transit management is a time consuming task. The Council will need to
start thinking about the long-term needs of the City and whether this bus makes
sense or not. We have not set aside any money in reserve to replace it as we
have with other departments and vehicles. This may be a service better handled
by the private sector or the school sector that has full time dedicated transit
managers and staff.
11.F Discussion and Action on Retail Motion
tabled from July 5th. I have previously forwarded or
delivered to each of you all of the material I have on this to date. You have
Bill Kelly’s letter, Wayne Marshall’s timelines and recommendations on
amendments to Comprehensive Plan and Zoning and outlines from the City Clerk on
timelines for referendums. The only new enclosure is a new motion from Larry to
amend Jim Roberts’s motion from July 5th (Pink).
Each of you has raised worthy concerns. This has been a
difficult issue and that there is frustration over both time and process. Please
keep in mind and communicate to others that there is no way to avoid process and
that process by its very nature -takes time.
This is a democracy where many are permitted the privilege
of participation. Over the last several months there has been a lot of
discussion on size itself, particular retail options, local retail needs and
jobs. Each of these items is a huge issue and it takes an understandable amount
of time to weigh through many large issues created by a single proposal. Once
the issues are decided it will take that same democratic process to implement
decisions. There is no magic motion that will implement any decision
immediately. City staff is here to help in any way that we can. Each of you has
been elected to represent the people on issues both large and small. However we
proceed, I encourage you to find a way to turn the intensity of today’s issue
into a long-term positive thing for the community.
|