|
MANAGER’S REPORT
For Council Meeting
Tuesday, May 1, 2007
TO: MAYOR AND CITY
COUNCIL
FROM: Terry St. Peter, City Manager
DATE: Friday, April 27, 2007
11.B City Park
Concession Bid. You have a bid for this in your packet. (Lilac)
11.C Airport Apron
Funding. Last year, probably around this same time, the city agreed to
construct an expanded aircraft-parking apron at the airport. We had applied for
and received federal funds to pay for the lion’s share of it. However, the
initial scope of work came in at over $1 million in costs, and we had only
$300,000 in federal funds. So, we negotiated down the amount of work, agreed to
bank on another $150,000 from the feds, and considered a method to raise the
balance of funds locally. I said then that we could proceed with a couple of
options and I probably would be back much later on with a plan for a loan to pay
any unfunded balances. (Blue)
Our “gamble” that we could
apply an additional $150,000 funds in grant money has paid off. The federal
government did continue the funding program and so we now can apply that money.
We didn’t consider that at serious risk, so we spent the money in anticipation
of the grant program continuing—it wasn’t guaranteed but it was likely. That
part is done.
Our plan also called for the
leasing of 12 hangar spaces at $13,000 apiece to generate $156,000 -- or to
lease enough to be able pay back a loan of up to $156,000. That, along with the
grants from federal and state government and our matching share, would make up
the amount of money needed. We also said at that time that getting all of the
leases signed during the first year may not be possible, but we could use of a
share of the $15,000 the city has already been raising annually to pay off a
loan to complete the project. The idea was to be able to complete the project,
at the minimum feasible level, and not pass any additional cost to the
taxpayer.
The project has been completed
and it looks good and we should start to see the private hangar construction
start any day now.
It is now time for us to settle
up the costs.
There have been five hangar
leases issued, one with an advance ten-year payment of $13,000, the others with
a lease agreement that has biannual escalator clauses. We are quite certain
that, once things get settled both financially and on the ground, there will be
more lease interest. We need to get our house back in order first.
I am enclosing an airport apron
expansion-financing plan. I am proposing that the city seek to borrow $131,000
and I have outlined the method to pay it back. Actually, I have obtained a bit
more information since I prepared that sheet and will be tweaking the proposal a
bit, to probably $145,000 to $150,000, by Tuesday night, but this will give you
the basic idea. I think if you read down the list, it will be fairly
self-explanatory and we can discuss it more Tuesday night.
The leases are for twenty years, so the city will earn
more money, probably for airport support, in the long run.
11.D Retail Zoning
Issues. Wayne has a paper to give some structure to this long-standing
issue. (Pink)
11.E Performance Center
Feasibility Committee. The Council has agreed to have Mayor Hurley,
Councilor Heberer and me to come up with a list of nominees for the Performance
Center committee. We have met and considered different people; some have been
contacted and some have not yet. Given what other activities have deterred us, I
think we need a few more days to complete this. This will let you know that we
are working on it, but I would ask that this item be tabled to the next meeting,
so that we can submit the list of people to you in writing in advance of any
votes.
11.G Executive Session
for a legal matter. This is for a report and discussion of a pending
legal settlement of a land-use dispute. There should be a formal vote afterward
to authorize me to sign a settlement agreement.
And, that’s it for this week . |